Question: Frances can complete a job in 12 hours, and Joan can complete the same job in 8 hours. Frances starts the job at 9 a.m., and stops working at 3 p.m. If Joan starts working at 4 p.m. to complete the job, at what time is the job finished?
- 6 p.m.
- 7 p.m.
- 8 p.m.
- 10 p.m.
- 12 p.m.
Correct Answer: C
Solution and Explanation
Approach Solution 1:
Considering the given case scenario of two workers Frances and Joan, it can be identified that Frances can work for 12 hours to complete a job. Joan can complete the same job in 8 hours. This can be implied as-
Frances- 1/12
Joan- 1/8
Based on the given scenario, Frances worked from 9am to and stopped working at 3pm. This equates to Frances working for 6 hours for the job. Accordingly, the amount of work he completed is equal to
1 ÷ 12 * 6 = ½
Joan is supposed to complete the work of Frances who did half of the work. This means that half of the remaining work is to be completed by Joan. accordingly, the time t that is required for Joan to complete the work can be equated with half of the work done by Frances. This equals to-
1 ÷ 8 * t= ½
\(\Rightarrow t=8* ^1/_2\)
\(\Rightarrow t=4\)
Hence, the time that would be required by Joan to complete the remaining half of the work is 4 hours. Accordingly, considering that Joan will start working from 4pm, his work would be completed by 8pm. Hence, C is the correct answer.
Approach Solution 2:
There is another method to solve the problem and get the answer.
One would be using the fact that when 2 or more people work towards the completion of work, then the sum of fractions of work done by each person is equal to 1. Here, 1 means work is completed by the person.
Let’s say, Joan takes x hours to complete the work which is what one needs to find from the problem.
The work completed by Frances in 1 hour is equal to = 1/12
Calculating the fraction of work done by Frances in 6 hours between 9am to 3pm is equal to 6/12. This implies that ½ of the work is completed by Frances in 6 hours.
Let us take the Work done by Joan in 1 hour is equal to ⅛, considering Joan takes 8 hours to complete his work.
Calculating the Fraction of work done by Joan in x hours will hence equal to x/8
Therefore, from the above evaluations it can be identified that when both the fractions are added, it gives the result one. This can be equated as-
1/2+ x/8= 1
4+x/8= 1
4 + x = 8
Accordingly, when the equation is resolved it gives the following results which can be identified as-
x = 4 hours
Therefore, Joan will take around four hours to complete the rest half of the work. While Joan will start his work from 4pm and take four hours to complete the work, it implies that the work will be completed by 8pm.
Hence, option C with 8pm as the answer is correct.
Approach Solution 3:
Frances worked 6 hours. Since she takes 12 hours for the whole job, she has done half the job.
Half the job remains for Joan to do.
Since Joan takes 8 hours for a whole job, she takes 4 hours for half a job.
So Joan will take 4 hours to finish the job.
Since she starts at 4 p.m., the job will be finished at 8 p.m.
“Frances can complete a job in 12 hours, and Joan can complete the same job in 8 hours”- is a topic of the GMAT Quantitative reasoning section of GMAT. To solve GMAT Problem Solving questions a student must have knowledge about a good amount of qualitative skills. GMAT Quant practice papers improve the mathematical knowledge of the candidates as it represents multiple sorts of quantitative problems.
Suggested GMAT Problem Solving Questions
- A Furniture Store Sells Only Two Models of Desks, Model A and Model B GMAT Problem Solving
- In a Drawer, There are 4 White Socks, 3 Blue Socks, and 5 Grey Socks GMAT Problem Solving
- There are 100 Apples in a Bag of which 98% are Green and Rest are Red GMAT Problem Solving
- A Palindrome is a Number That Reads the Same Forward and Backward. GMAT Problem Solving
- Three Cars Leave From A To B In Equal Time Intervals GMAT Problem Solving
- Jug Contains Water And Orange Juice In The Ratio 5:7 GMAT Problem Solving
- A Tank, Which Usually Takes 5 Hours to be Filled, Takes 6 Hours to Fill Because of a Leak GMAT Problem Solving
- There are 6 Tasks and 6 Persons. Task 1 Cannot be Assigned Either to Person 1 or to Person 2; Task 2 Must be Assigned to either Person 3 or Person 4 GMAT Problem Solving
- A Manufacturing Company is Testing out a New Design for One of its Most Popular Products GMAT Problem Solving
- A Contract is to be Completed in 46 days and 117 Men Were set to Work, each Working 8 hours a Day GMAT Problem Solving
- An Inlet Pipe can Fill in an Empty Cistern in 30 minutes GMAT Problem Solving
- At a Certain Laboratory, Chemical Substances are Identified by an Unordered Combination of Three Different Colours GMAT Problem Solving
- Iqbal Dealt Some Cards to Mushtaq and himself from a Full Pack of Playing Cards GMAT Problem Solving
- A Zookeeper Counted the Heads of the Animals in a Zoo and Found it to be 80 GMAT Problem Solving
- A Shop Stores x kg of Rice. The First Customer Buys half this Amount Plus half a kg of Rice GMAT Problem Solving
- In a Class of 120 Students Numbered 1 to 120, All Even Numbered Students Opt for Physics GMAT Problem Solving
- A and B are Two Alloys of Gold and Copper Prepared By Mixing Metals in GMAT Problem Solving
- For integers x and y, 2^x+2^y=2^30. What is the value of x+y? GMAT Problem Solving
- United Telephone charges a base rate of $10.00 for service, plus an additional charge of $0.25 per minute. Atlantic Call charges a base rate of $12.00 for service GMAT Problem Solving
- Lamp A Flashes Every 6 seconds, Lamp B Flashes Every 8 seconds, Lamp C Flashes Every 10 seconds GMAT Problem Solving
- At a Sandwich Shop, There are 2 Breads, 3 Kinds of Meat, 4 Types of Cheeses GMAT Problem Solving
- A Survey was Conducted Among 1000 People to Know About their Eating Habits GMAT Problem Solving
- Jake Rides His Bike for the First 2/3 of the Distance From Home to School GMAT Problem Solving
- Two Trains Running in Opposite Directions Cross a Man Standing on the Platform GMAT Problem Solving
- Initial Population of a Town was 8000 PeopleGMAT Problem Solving
- The Volume of a Sphere with Radius r is (4/3)*pi*r^3. A Solid Sphere GMAT Problem Solving
- Which of the Following is Equal to 5^17×4^9? GMAT Problem Solving
- In a Shooting Competition, Probability of A Hitting Target is 2/5, by B is 2/3 and C is 3/5 GMAT Problem Solving
- The Sides of a Quadrilateral Taken in Order are 16,16,14 and 10 GMAT Problem Solving
- If 80 Lamps Can Be Lighted, 5 Hours Per Day For 10 Days GMAT Problem Solving
- If
denotes the area of a circle with diameter d, then which of the following is equal to <4>*<6> GMAT Problem Solving - At exactly what time past 7:00 will the minute and hour hands of an accurate working clock be precisely perpendicular to each other for the first time? GMAT Problem Solving
- There is a 120 Liter Mixture of Alcohol and Water GMAT Problem Solving
- When X Is Divided By 13, The Answer Is Y With a Remainder of 3. GMAT Problem Solving
- If a/b = 2/3 Which of the Following is Not True? GMAT Problem Solving
- 1/3 of the Cookies in a Jar are Chocolate Chip, 2/3 of the Remaining Cookies are Peanut Butter GMAT Problem Solving
- The Kinetic Energy K, in Joules, Provided by the Mass of a Particle m GMAT Problem Solving
- A Recent Survey Showed That 50 Percent of People Polled Believe that Elected Officials Should Resign GMAT Problem Solving
- The Perimeter of a Square is Equal to the Perimeter of a Rectangle Whose Length And Width are 6m and 4m Respectively GMAT Problem Solving
- The Closing Price of Stock X Changed on Each Trading Day Last Month GMAT Problem Solving
- An Exam Consists of 8 True/False Questions GMAT Problem Solving
- In a Certain Store, the Profit is 320% of the Cost GMAT Problem Solving
- If y is the Smallest Positive Integer Such That 3,150 Multiplied By y is the Square of an Integer GMAT Problem Solving
- If mn ≠ 0 and 25 Percent of n Equals 37 1/2 Percent of m, What is the Value of 12n/m? GMAT Problem Solving
- What is the Largest Five-Digit Number which is Divisible by 17? GMAT Problem Solving
- If x is not equal to zero, and x + 1/x = 3, then what is the value of x^4 + 1/x_4? GMAT Problem Solving
- An Isosceles Right Triangle With a Leg of Length "a" And Perimeter "p" GMAT Problem Solving
- The Light In A Restroom Operates With a 15-Minute Timer GMAT Problem Solving
- Two Pipes Together Can Fill a Tank In 35 Minutes GMAT Problem Solving
- In a Shop, The Marked Price of an Article is Worked Out in Such a Way That it Generates a Profit of 33 1 by 3 GMAT Problem Solving
Comments