Question: A is twice as good a workman as B and together they finish a piece of work in 16 days. In how many days will A alone finish the work?
(A) 20 days
(B) 23 days
(C) 24 days
(D) 25 days
(E) 27 days
Correct Answer: C
Solution and Explanation:
Approach Solution 1:
The problem statement states that:
Given:
- A is twice as good a workman as B and together they finish a piece of work in 16 days.
Find out:
- The number of days A alone will finish the work.
The given sum can be solved by using the mathematical equation of work, time and efficiency. The problem given illustrates that the Efficiency of A equals that of 2 times of Efficiency of B. They together can complete the whole work in 18 days.
Hence using the formula: Work = Efficiency × Time.
The calculation goes like this:
Efficiency of A: Efficiency of B = 2: 1
Efficiency of (A + B) = 3
Total Work = 3 x 16 = 48 units
A alone can do this work in 48/2 days [Total work/efficiency of A]= 24 days.
Therefore, the time taken by A to complete the work is 24 days.
Approach Solution 2:
The problem statement implies that:
Given:
- A is twice as good a workman as B and together they finish a piece of work in 16 days.
Find out:
- The number of days A alone will finish the work.
Let’s consider that B does x [p.o.w/day] and A does 2x [p.o.w/day].
Here. where p.o.w stands for pieces of work.
Now, we know that together they finish 1 p.o.w in 16 days.
Putting the information in an equation, we have
(x+2x) \(\frac {p.o.w}{day}*16days=1p.o.w\)
\(x=\frac{1}{48}\frac{p.o.w}{day}\)
Now, we know that B does 1/48 [p.o.w/day]and A does 2/48 [p.o.w/day].
Finally, to find in how many days A alone will finish 1p.o.w we can use
\(\frac{2}{48}\frac{p.o.w}{day}*y days= 1 p.o.w\)
y = 24 days
Hence, A will finish in 24 days one piece of work.
Approach Solution 3:
The problem statement suggests that:
Given:
- A is twice as good a workman as B and together they finish a piece of work in 16 days.
Find out:
- The number of days A alone will finish the work.
As per the condition of the question, A : B = 2 : 1
=> A = 2/3
A and B together finish a piece of work in 16 days.
Therefore, work done by A+B= 1/16.
Therefore, work done by A alone = 2/3 * 1/16 = 2/48 = 1/24
Hence, the number of days A alone will finish the work = 24 days.
“A is twice as good a workman as B and together they finish a piece”- is a topic of the GMAT Quantitative reasoning section of the GMAT exam. To solve the GMAT Problem Solving questions, the candidates must have a basic knowledge of arithmetic, geometry and algebra. The candidates can follow the GMAT Quant practice papers to practise varieties of questions that will help them to improve their mathematical skills.
Suggested GMAT Problem Solving Questions
- If x^9= 9^9^9, What is the Value of x? GMAT Problem Solving
- In a Competition, a School Awarded Medals in Different Categories GMAT Problem Solving
- In how many ways can 5 apples (identical) be distributed among 4 children? GMAT problem solving
- What is Greatest Positive Integer n such that 2^n is a Factor of 12^10? GMAT Problem Solving
- All the five digit numbers in which each successive digit exceeds its GMAT Problem Solving
- A box contains two white balls, three black balls and four red balls GMAT Problem Solving
- Consider An Obtuse-Angled Triangles With Sides 8 Cm, 15 Cm GMAT Problem Solving
- I Travel The First Part Of My Journey At 40 Miles Per Hour GMAT Problem Solving
- Profit Earned By Selling An Article At 1060 Is 20 % More Than The Loss GMAT Problem Solving
- A Perfect Square is a Number that Becomes an Integer when Square GMAT Problem Solving
- If x + y = 2 and x^2 + y^2 = 2, What is the Value of xy? GMAT Problem Solving
- The Owner of A Local Jewellery Store Hired 3 Watchmen to Guard his Diamonds GMAT Problem Solving
- What is the smallest integer n for which 25^n>5^12 GMAT Problem Solving
- Ten Coins are Tossed Simultaneously. In how many of the Outcomes GMAT Problem Solving
- A Pool can be Filled in 4 Hours and Drained in 5 Hours GMAT Problem Solving
- If x^2 − 2 < 0, which of the following specifies all the possible GMAT Problem Solving
- The Mass Of 1 Cubic Meter Of A Substance Is 800 Kilograms GMAT Problem Solving
- A Dairyman Pays Rs. 6.40 Per Liter Of Milk GMAT Problem Solving
- A Train Approaches A Tunnel AB. Inside The Tunnel Is A Cat Located GMAT Problem Solving
- John is 20 years older than Brian. 12 years ago, John was twice as old GMAT Problem Solving
- A Train Overtakes Two Persons Who Are Walking In The Same Direction GMAT Problem Solving
- If 1/x − 1/x+1= 1/x+4, Then x could be GMAT Problem Solving
- If x = - |x|, Then Which One of the Following Statements GMAT Problem Solving
- A Bag Contains 4 Red and 3 Black Balls. A Second Bag Contains 2 Red GMAT Problem Solving
- A Mixture of 40 Litres of Milk and Water, Contains 20% of Water GMAT Problem Solving
- A Candidate is Required to Answer 6 Out of 10 Questions Divided into 2 Groups GMAT Problem Solving
- Company XYZ had $498.2 Million in Profits for the Year GMAT Problem Solving
- If -2 < a < 11 and 3 < b < 12, Then Which of the Following is NOT Always True GMAT Problem Solving
- Karan and Arjun run a 100-metre Race, Where Karan Beats Arjun by 10 metres GMAT Problem Solving
- The Figure below Shows an Equilateral Triangle ABC Tangent GMAT Problem Solving
- Three groups of children contain respectively 3 girls and 1 boy GMAT Problem Solving
- If x=10^{10},\frac{x^2+2x+7}{3x^2-10x+200} is closest to GMAT Problem Solving
- If set S Consists of all Different Solutions of Equation |x – 4| = x, What is the Range of Set S GMAT Problem Solving
- Set T consists of all points (x, y) such that \(x^2+y^2=1\) GMAT Problem Solving
- How Many Natural Numbers Not Exceeding 4321 can be Formed GMAT Problem Solving
- In an Isosceles Triangle PQR, If ∠Q = 80 Degrees, Then What is The GMAT Problem Solving
- Two Members of a Club are to be Selected to Represent the Club GMAT Problem Solving
- The Square Root of 24336 is Exactly GMAT Problem Solving
- A Certain Purse Contains 30 Coins, Each Coin is either a Nickel or GMAT Problem Solving
- Which of the Following is Equal to the Value of 2^5+2^5+3^5+3^5+3^5 ? GMAT Problem Solving
- The Price of a Certain Painting Increased By 20% During the First Year GMAT Problem Solving
- The Population of the Village is 5500. If the Number of Males Increase GMAT Problem Solving
- Machine A Produces 100 Parts Twice as Fast as Machine B does GMAT Problem Solving
- The Difference Between a Two-Digit Number and the Number Obtained GMAT Problem Solving
- Which of the following is always equal to sqrt(9+x^2-6x)?GMAT Problem Solving
- A Colony has Houses Numbered 1 to 150 GMAT Problem Solving
- Two Vessels A and B Contain Milk and Water Mixed in the Ratio 8:5 GMAT Problem Solving
- A Dealer Offers a Cash Discount of 20%. Further, a Customer Bargains GMAT Problem Solving
- If a Regular Hexagon is Inscribed in a Circle with a Radius of 4, The GMAT Problem Solving
- There are Two Vessels A and B. Vessel A is Containing 40 Litres of GMAT Problem Solving
Comments