A is Twice as Good a Workman as B and Together They Finish a Piece GMAT Problem Solving

Question: A is twice as good a workman as B and together they finish a piece of work in 16 days. In how many days will A alone finish the work?

(A) 20 days
(B) 23 days
(C) 24 days
(D) 25 days
(E) 27 days

Correct Answer: C

Solution and Explanation:
Approach Solution 1:

The problem statement states that:
Given:

  • A is twice as good a workman as B and together they finish a piece of work in 16 days.

Find out:

  • The number of days A alone will finish the work.

The given sum can be solved by using the mathematical equation of work, time and efficiency. The problem given illustrates that the Efficiency of A equals that of 2 times of Efficiency of B. They together can complete the whole work in 18 days.

Hence using the formula: Work = Efficiency × Time.
The calculation goes like this:
Efficiency of A: Efficiency of B = 2: 1
Efficiency of (A + B) = 3
Total Work = 3 x 16 = 48 units

A alone can do this work in 48/2 days [Total work/efficiency of A]= 24 days.
Therefore, the time taken by A to complete the work is 24 days.

Approach Solution 2:
The problem statement implies that:
Given:

  • A is twice as good a workman as B and together they finish a piece of work in 16 days.

Find out:

  • The number of days A alone will finish the work.

Let’s consider that B does x [p.o.w/day] and A does 2x [p.o.w/day].
Here. where p.o.w stands for pieces of work.

Now, we know that together they finish 1 p.o.w in 16 days.
Putting the information in an equation, we have

(x+2x) \(\frac {p.o.w}{day}*16days=1p.o.w\)

\(x=\frac{1}{48}\frac{p.o.w}{day}\)

Now, we know that B does 1/48 [p.o.w/day]and A does 2/48 [p.o.w/day].
Finally, to find in how many days A alone will finish 1p.o.w we can use

\(\frac{2}{48}\frac{p.o.w}{day}*y days= 1 p.o.w\)

y = 24 days
Hence, A will finish in 24 days one piece of work.

Approach Solution 3:
The problem statement suggests that:
Given:

  • A is twice as good a workman as B and together they finish a piece of work in 16 days.

Find out:

  • The number of days A alone will finish the work.

As per the condition of the question, A : B = 2 : 1
=> A = 2/3

A and B together finish a piece of work in 16 days.
Therefore, work done by A+B= 1/16.

Therefore, work done by A alone = 2/3 * 1/16 = 2/48 = 1/24

 Hence, the number of days A alone will finish the work = 24 days.

“A is twice as good a workman as B and together they finish a piece”- is a topic of the GMAT Quantitative reasoning section of the GMAT exam. To solve the GMAT Problem Solving questions, the candidates must have a basic knowledge of arithmetic, geometry and algebra. The candidates can follow the GMAT Quant practice papers to practise varieties of questions that will help them to improve their mathematical skills.

Suggested GMAT Problem Solving Questions

Fees Structure

CategoryState
General15556

In case of any inaccuracy, Notify Us! 

Comments


No Comments To Show