A Contractor Estimated that his 10-Man Crew Could Complete the Construction in 110 Days if There Was no Rain.

Sayantani Barman logo

bySayantani Barman Experta en el extranjero

Question: A contractor estimated that his 10-man crew could complete the construction in 110 days if there was no rain. (Assume the crew does not work on any rainy day and rain is the only factor that can deter the crew from working). However, on the 61st day, after 5 days of rain, he hired 6 more people and finished the project early. If the job was done in 100 days, how many days after day 60 had rain?

  1. 1.7
  2. 2.7
  3. 3.4
  4. 5.4
  5. 8

“A contractor estimated that his 10-man crew could complete the construction in 110 days if there was no rain. ”– is a topic of the GMAT Quantitative reasoning section of GMAT. This question has been taken from the book “GMAT Quantitative Review”. To solve GMAT Problem Solving questions a student must have knowledge about a good amount of qualitative skills. The GMAT Quant topic in the problem-solving part requires calculative mathematical problems that should be solved with proper mathematical knowledge.0

Answer
Approach Solution 1

Given: 10-man crew needs 110 days to complete the construction.

On the 61\(^{st}\) day, after 5 days of rain……: as it was raining for 5 days then they must have been working for 55 days thus completing ½ of the job, ½ is left (55 days of work for 10 men).

The contractor “hired 6 more people”: speed of construction increased 1.6 times, so the new 16- men crew needed \(\frac{55}{1.6}\approx 34.4\) days to complete the construction, but after they were hired the job was done in 100 – 60 = 40 days. Therefore, it rained for 5 days. (They needed MORE than 34 days to finish the job, so if it rained for 6 days they wouldn’t be able to finish the job in 100 (40) days.

Correct option: B

Approach Solution 2

Total work = 10 persons * 110 days = 1100 person-days

Work completed till it rained for 5 days = 10 person * 55 days = 550 person-days.

Pending work = 1100 – 550 = 550 person-days

Ideally, from 61\(^{st}\) day to 100th day, the manpower rose to 16, which means they can do a work of = 16 person * 40 days = 640 person-days

But the remaining work is only 550 person-days, so the difference is 640 – 550 = 90 person-days.

Therefore, it rained for = \(\frac{90}{16}\) = 5.625 person-days

Hence, work happened = 40 – 5.6 = 34.4 days

Hence it rained for 5 more days.

Correct option: B

Suggested GMAT Quant Questions

Fees Structure

CategoryState
General15556

In case of any inaccuracy, Notify Us! 

Comments


No Comments To Show